Client

Dragages

Year

2022

GFA

1.16 km

Location

Hong Kong

Causeway Bay / Admiralty Transit Tunnels

BIM Authoring, Virtual Reality, LOD400

Porfolio Hero Image_edited.jpg
Portfolio curve off-white.png
Portfolio curve off-white.png
Porfolio Hero Image_edited.jpg
Portfolio curve.png

Causeway Bay / Admiralty Transit Tunnels

​

Continent

Asia

Location

​

Client

Dragages

GFA

1.16 km

Year

2022

Portfolio curve.png

Back To Portfolio

Project

The main scope and challenge in this project is the construction of the Eastern Tunnels and Western Tunnels by Tunnel Boring Machine (TBM). Meticulous project planning is essential in aiding the TBMs.

We built the BIM models including architectural, civil, structural and MEP for permanent structure developed from 2D working drawings from the client. The client then utilized the models to identify potential clashes to resolve constructibility issues.